WGLHA Preliminary Dredging Schedule  Date:  August 16, 2022 

Goal: to remove 400 to 500 cubic yards of material each day.  

Setup:

 8-22-22 to 8-24-22 

Note:  the plan will be to start at the furthest point from the proposed storage areas. 

 Area 2: 

     7 to 8 days. 8-24-22 to 8-31-22 

Area 1: 

     5 to 6 days. 9-1-22 to 9-6-22 

Area 7: 

     3 to 4 days. 9-7-22 to 9-10-22 

Area 6:

     1 day. 9-11-22 

Area 5A:

     3 to 4 days. 9-12-22 to 9-15-22 

Area 5B:

      3 to 4 days. 9-16-22 to 9-19-22 

Area 3 and 4: 

   1 day of blasting/leveling. 9-20-22 

Note:  this is an estimate based on the minimum amount our dredge can remove daily. If things go well and we get more daily the timeliness could move up. We will keep daily logs on what is being removed and update the community as we finish each area.